The Seattle City Council is currently deliberating a proposal aimed at streamlining the permitting process for Sound Transit light rail projects, but discussions took a turn when an amendment introduced by District 4 Councilmember Maritza Rivera raised concerns among committee members.
This amendment, brought forward unexpectedly, has necessitated the postponement of a crucial vote in the Land Use Committee, highlighting the complexities involved in managing public outreach for these transit initiatives.
Mayor Bruce Harrell’s proposed code amendments earlier this year aimed to simplify Seattle’s land use codes, which were not originally crafted with light rail infrastructure in mind.
The proposed changes endeavor to expedite the approval timeline for Sound Transit permits across various critical areas, including station design and tree removal.
Under the existing regulations, the West Seattle and Ballard Link Extension light rail projects could face 19 different types of development standards, complicating the process significantly.
Currently, average permitting timelines for new light rail stations in Seattle exceed 200 days.
Harrell’s goal is to curtail this duration to under 100 days through his reform initiative.
However, Rivera’s recently proposed amendment introduces a new framework for community engagement, potentially extending the time and costs associated with the permitting process.
This amendment would require Sound Transit to present a comprehensive Community Outreach Plan (COP) before any permit application can be submitted.
As a result, this could significantly alter the approval workflow, demanding Sound Transit to provide in-depth documentation on stakeholder outreach, methods of communication, and public feedback mechanisms — elements that are not currently mandated by existing city codes.
The COP would necessitate detailing resident and business contact information, communication strategies encompassing print, digital, and in-person formats, outreach objectives, and relevant project information that would be shared during the outreach process.
Further complicating the situation, each permit application submitted by Sound Transit would require compliance documentation related to the COP.
This documentation must include a record of community members and stakeholders contacted, a summary of community feedback, and an explanation when feedback is not incorporated into the project design.
Additionally, the Seattle Department of Construction and Inspections (SDCI) would have to broadcast the information that permits can be appealed to King County Superior Court, a step that could further delay the approval process.
Rivera argued that her amendment was merely a formalization of existing practices rather than introducing new requirements.
However, questions quickly arose regarding the impact of the amendment on the permitting timeline and overall project cost.
Council Central Staff Analyst Ketil Freeman pointed out that the new requirement for a Community Outreach Plan was not included in the city’s proposed code or the mayor’s initiative.
Sound Transit Program Director Sara Maxana also expressed concerns about whether these requirements were uniquely applicable to Sound Transit projects or if they would set a new precedent affecting all development permits.
Due to the uncertain implications raised by Councilmembers Dan Strauss and Alexis Mercedes Rinck, the committee chair Mark Solomon ultimately decided to delay the vote for a week.
Rinck emphasized the urgency to grasp the full impact of the amendment, conveying the need to balance community engagement with the pressing deadlines associated with delivering the light rail projects.
“The public has voted to approve these projects, has been paying for them for years, and we shouldn’t force them to keep paying while progress is stalled,” Rinck stated, highlighting the broader need for efficiency.
In support of Rivera’s proposal, Councilmember Cathy Moore assured her colleagues that the amendment would not result in significant delays or costs, commenting that regardless of slight increases in expenditure, proper public engagement was necessary.
Rivera expressed surprise at the concerns surrounding her proposal, clarifying that it was intended to bolster transparency in the permitting process rather than impede it.
She stated, “If showing our work is a heavy lift and a problem, then I have bigger concerns than I had actually coming into this amendment, that was not meant to stall the project or to create an obstacle.”
Despite these assurances, the likelihood remains that additional documentation and new outreach processes will create hurdles to the timely completion of the projects.
With 89 permits needed for West Seattle Link alone, managing multiple projects concurrently is already a demanding task.
The Land Use Committee is anticipated to revisit the amendment and the broader proposal ahead of a final vote scheduled for Wednesday, June 4 at 2 PM.